East Elementary Project May Be Completed In Time For Start Of 2014-2015 School Year

Date posted - September 11, 2013

Sheldon-Schools-logoSheldon, IA — There is an 80 percent chance that the Sheldon East Elementary Construction/Renovation Project may be completed in time for the start of next school year.  Superintendent Robin Spears reported that information to the School Board during their regular monthly meeting Wednesday evening.

Spears says the project’s General Contractor laid out a timetable in a Wednesday construction meeting.  Spears says the timetable calls for asbestos removal from the lunch room ceiling and floor to be completed over the Christmas holiday break.  Asbestos is to be removed from the tunnels in March. He told the Board that the District should have a small window in August next year that will allow them to get moved into the building, and get everything ready to start school the day after Labor Day next year in the completed building.

Spears also reported to the Board on the Ball Field/Recreation Project.  He told the Board that Board members Randy Merley and Susan Rensink will be meeting with representatives of the City of Sheldon in the near future to finalize specifications for the project.  He says that after the specs have been finalized, they will be brought to the Board and to the City Council for final approval, before they begin the bidding process.  On a related note, Spears says that, although a sidewalk along Highway 18 on the north side of the new fields is not part of the project, one will be installed once work on the ball field project is done.

The Board also approved a change in Roofing Contractor for the East Elementary Project.  Superintendent Spears said the change was necessary after the original low bidder, Winkler Roofing, voluntarily withdrew their winning bid after they discovered that they may not be able to obtain the product necessary to do the work as specified in the contract.  Spears said that H&S Roofing from Spencer has now agreed to match the original Winkler bid for the job.  The Board unanimously approved the change.

In other action, the Board approved Open Enrollment Applications for a trio of siblings who have recently moved from the Sibley-Ocheyedan District into the Sheldon District, but wish to open enroll back into the Sibley-Ocheyedan District.

They also approved contracts for:  Ben Chestnut as 9th Grade Wrestling Coach; Dave Gross as Elementary ELL Associate; Monica Honkomp as Middle School Food Service Worker; Brooke Oldenkamp as EL Special Education Instructional Associate; and Nancy Rosenboom as the Elementary Principal’s Secretary, as well as dispatching several other agenda items.

The regular October meeting of the Board will be held Thursday, October 10th at 6:00 pm in the high school library.

Print Friendly

2 Responses to “East Elementary Project May Be Completed In Time For Start Of 2014-2015 School Year”

  1. Doug says:

    A little clarity por favor?

    “and get everything ready to start school the day after Labor Day next year”

    Is this a hint that school is going to start September 2nd next year?

    • kiwa says:

      Doug:

      The plan at this point is to push the first day of the 2014-15 school year back until Tuesday, September 2, 2014, to allow the building project to be completed prior to the start of the school year. The District made a similar calendar adjustment a few years ago when the new middle school opened.

      It should be noted, however, that as of this writing the 2014-15 school calendar hasn’t been completed, so nothing is set in stone.

      Thanks for your question!!

      Tom Traughber
      KIWA-AM/FM Radio

Leave a Reply

Sheldon Broadcasting Company, Inc. appreciates your comments that abide by the following guidelines:
1. Avoid profanities or foul language.
2. Disagree, but avoid ad hominem (personal) attacks.
3. Threats are treated seriously and will be reported to law enforcement.
4. Spam and advertising are not permitted in the comments area.
These guidelines are very general and cannot cover every possible situation. Please don't assume that Sheldon Broadcasting Company, Inc. or its advertisers agrees with or otherwise endorses any particular comment. We reserve the right to filter or delete comments or to deny posting privileges entirely at our discretion. Please note that comments are reviewed by the selected staff and may not be posted immediately. If you feel your comment was filtered inappropriately, please email walt@kiwaradio.com.


Back to:East Elementary Project May Be Completed In Time For Start Of 2014-2015 School Year