Sioux Center, Iowa (Sioux County Radio) — Highway 75 through Sioux Center is expected to reopen to traffic sometime this afternoon, Nov. 19th, ahead of the schedule project officials outlined last week.

Craig Lauritzen of DGR Engineering had previously said crews were targeting a reopening by the end of Friday, but the latest update indicates traffic could return to the road by mid- to late afternoon Thursday.

Final Touches Being Completed

Lauritzen says major work on the project is now complete, including street lighting, decorative concrete, and much of the landscaping.

Crews have also been installing synthetic turf in the medians and completing roadside landscaping work, including spreading topsoil, seeding and applying fiber mulch before winter.

Even after the highway reopens, drivers should expect to see work crews in the area for a few more days.

He said some minor landscaping and seeding touch-up work will likely be completed next year.

Four-Year Project Reaches the Finish Line

The reopening marks the completion of the final phase of Sioux Center’s Highway 75 reconstruction project.

This year’s work focused on the section from 5th Street North to just south of the 12th Street North intersection near McDonald’s.

The approximately $54 million project, which began in 2023, rebuilt roughly 2.5 miles of Highway 75 through the city. Improvements include two travel lanes in each direction, turn lanes, medians, sidewalks, and pedestrian crossings.

Sioux Center held an official ribbon-cutting ceremony for the project on Oct. 12.