Rock Valley Explores Data Center With PathOne, Sets November 24th Public Meeting

(Rock Valley Watertower - KIWA Staff Photo)

Rock Valley, Iowa (Sioux County Radio) — Rock Valley Economic Development is exploring a data center in the city’s business park with PathOne, the company pursuing a separate project at Perkins Corner southwest of Hull.

Economic Development Director Adam Rosman says Rock Valley’s facility would likely start smaller than the one proposed near Hull.

Residents can hear from PathOne and ask questions Tuesday, Nov. 24th, from 5:30 to 6:30 p.m. at the Parkview Event Center, 1303 10th Street. Rock Valley Economic Development and PathOne are hosting the free, open-to-the-public meeting.

Why Rock Valley is Interested

Rosman told reporters that Rock Valley’s machine shops already have openings to fill. That figures into the kinds of employers he wants to bring to town.

Asked who might use a local data center, Rosman pointed to banks, the hospital, and businesses that rely on connected equipment.

Whether any local businesses would sign on as customers is still an open question. PathOne representative Gyles Uhlenhopp described what has to happen before those conversations begin.

How Rock Valley Compares with Perkins Corner

Rosman described the Rock Valley concept as an “edge data center,” which puts computing and storage closer to the businesses using them. For comparison, PathOne has outlined a data center of up to 25 megawatts at Perkins Corner southwest of Hull. The company says it builds in 10-megawatt blocks of about 40,000 square feet each. Rosman said the Rock Valley facility would likely start smaller, though he did not give a specific capacity.

Uhlenhopp said the two sites caught PathOne’s attention for much the same reason.

The Perkins Corner project is further along. Uhlenhopp said PathOne has submitted its conditional-use permit application to Sioux County. If the application advances as anticipated, he expects two county bodies to review it in Orange City on Dec. 10th.

What Would Have to Happen in Rock Valley?

Rock Valley Economic Development owns the business park land, and Rosman said its board would have to approve a sale. The city would also work with PathOne on an operating agreement covering utilities and other site requirements. Asked whether Rock Valley would offer the developer tax breaks, Rosman said:

The industrial zoning rules Rock Valley publishes do not list data centers by name. The city’s zoning administrator can determine which category fits. New industrial construction requires a zoning permit and site plan. If the city classifies the facility as a conditional use, the ordinance also calls for a public hearing.

Uhlenhopp said PathOne wants to hear from residents before the Rock Valley plans take shape.

Estherville Takes First Vote on Data Center Rules

PathOne has also expressed interest in Estherville’s South Industrial Park. The Estherville City Council voted 5-1, with one abstention, on Nov. 16th to approve the first reading of a zoning amendment that would limit data centers to 25 megawatts. Two readings remain before final adoption. The city’s Planning and Zoning Commission is tentatively set to revisit sound limits November 23rd.

Emmet County’s one-year moratorium, adopted in August, covers data center applications in unincorporated areas. Estherville’s proposed rules would govern development inside city limits.

Share: