Spencer, Iowa (RI) — Officials from Clay, Dickinson, and Emmet counties have approved a drainage district agreement for the proposed Red Rock Wind Energy Center.

The agreement addresses protection of drainage infrastructure such as ditches and tile lines that may be affected during construction of the wind farm.

Developer Invenergy plans to build 51 wind turbines in Dickinson and Emmet counties. Clay County will host the project’s grid connection and portions of its underground electrical lines.

Invenergy representative Manashree Padiyath said the company will reimburse the drainage district for administrative and inspection costs associated with the project.

Major construction on the Red Rock Wind Energy Center is expected to begin next year, with the project slated for completion in late 2028 or 2029.